California Borough Council Thursday approved two change orders that reduced the cost of the new sewerage installation project by more than $93,000.

The first change approved was a $10,076 reduction in the paving contract with Morgan Excavating; the second was an $83,712 deduction for sewer line installation for the Malden and Granville areas by contractor Glenn Johnson.

 